Average Daily Workforce: 600 workers
-
Planned Concrete Utilization: 25,000 m³ (enough to fill 10 Olympic-sized swimming pools)
-
Estimated Electrical Cable Installation: 445 km (beyond Dubai to Abu Dhabi)
-
Planned Glass Panel Weight: 492,000 kg (about 1.25 times the weight of a Boeing 747)
-
Projected Brickwork Area: 30,247 m² (if stacked vertically, would reach 378 km high)
-
Building Structure & Built-up Area: 1 Ground, 1 Podium, 14 Floors + Roof; Built-up Area: 276,600 sq ft
-
Construction Start Date: 6 October 2023
-
Workforce Nationalities Represented: Minimum 15
-
Estimated Rebar Length: 2,900 km (spanning far beyond Dubai to Muscat)
-
Projected Building Weight: Approx. 3,500 tons (combined structural materials)
-
Rooftop Track Distance (Upon Completion): 52.6 laps = half a marathon
-
Estimated Total Man-Hours: 131,000 hours (equivalent to 3,638 round trips to the moon)
-
Planned Landscaped Area: 3,914 m² (equal to 18 mini forests of 200 m² each)
-
Number of Elevators: 4 (travel a combined 1.18 km daily)







GOUND FLOOR - FOUNDATION CASTING

PREPARATION FOR PODIUM LEVEL VERTICAL ELEMENTS

EXCAVATION

EXCAVATION AND SURFACE LEVELING OF FOUNDATIONS AND UNDERGROUND WATER TANK

FOUNDATIONS CASTING IN PROGRESS

RAFT FOUNDATION PREPARATION AND PCC WORKS

PODIUM SLAB CONCRETING

SECOND FLOOR IN PROGRESS

SECOND FLOOR CONCRETE WORKS ONGOING

FOURTH FLOOR CONCRETE WORKS ONGOING

FOURTH FLOOR IN PROGRESS

SIXTH FLOOR CONCRETE CASTING

10th Floor Slab in Progress

10th Floor Slab in Progress

10th Floor Slab in Progress