Average Daily Workforce: 300 workers
-
Planned Concrete Utilization: 9,000 m³ (enough to fill 3.5 Olympic-sized swimming pools)
-
Estimated Electrical Cable Installation: 205 km (equivalent to the distance from Dubai to Abu Dhabi)
-
Planned Glass Panel Weight: 192,000 kg (around half the weight of a Boeing 747)
-
Projected Brickwork Area: 12,147 m² (if stacked vertically, would reach 140 km high)
-
Construction Start Date: 23 March 2024
-
Building Structure & Built-up Area: 1 Basement, 1 Ground, 5 Floors + Roof; Built-up Area: 163,300 sq ft
-
Workforce Nationalities Represented: Minimum 15
-
Estimated Rebar Length: 1,050 km (distance from Dubai to Muscat)
-
Projected Building Weight: Approx. 1,200 tons (combined structural materials)
-
Rooftop Track Distance (Upon Completion): 200 m track = half a marathon after multiple laps
-
Estimated Total Man-Hours: 476,000 hours (equivalent to 1,322 round trips to the moon)
-
Planned Landscaped Area: 1,200 m² (equal to six mini forests of 200 m² each)
-
Number of Elevators: 2 (travel a combined 0.6 km daily)










Second Floor Slab in Progress

First Floor Slab in Progress

Ground Floor Slab in Progress

Ground Floor Slab in Progress

Ground Floor Slab in Progress

Ground Floor Slab in Progress